The Brief
September 27, 2026  ·  8 min read
The story
The pipe under the data centre

Project Jupiter is built to run on its own fuel-cell power plant. The plant needs gas from a single new pipeline, and two regulators have deadlines to decide on the plant's air permit and the pipe before Oracle's own December condition comes due.

Aerial view of the Project Jupiter campus under construction in southern New Mexico: a large flat-roofed data hall with steel framing at one end, a tower crane lowering a line, a concrete pump truck at its base, and dozens of trucks and machines on graded desert ground around it.

On September 24, Bloomberg reported that Oracle had sent the developer of Project Jupiter, a unit of Blue Owl Capital, a notice citing force majeure, according to people familiar with the situation who asked not to be named. In Bloomberg's account, Oracle is not trying to walk away as the site's main tenant; it is seeking to put off payments should the data centre get derailed. Oracle has filed nothing on it. Oracle's stock closed down 3.47% that day, on a day when other news was also moving markets, so the report cannot be credited with the whole move.

Oracle's reply was direct. A spokesperson said such notices are commonplace and do not by themselves establish a delay, and the company told CNBC that Project Jupiter remains on our planned schedule. The reel you watched is about why the schedule is worth reading closely anyway: the campus depends on one pipe, and the pipe and the power plant each sit in front of a regulator with a deadline.

Where it landed

Project Jupiter is one of the Stargate sites announced by SoftBank, OpenAI and Oracle, in Doña Ana County, New Mexico. The county describes a potential investment of up to $165 billion over 30 years, with a minimum initial investment of $50 billion and a first phase anticipated in the third quarter of 2028. The campus is under construction. Oracle is the tenant, and the project is led by STACK Infrastructure in partnership with BorderPlex Digital Assets.

Fuel-cell plant
Bloom fuel cells
up to 2.45 GW
Oracle pays all energy
The pipe
Energy Transfer unit
17.77 miles
one shipper: Oracle unit
In-service date
revised estimate
Feb 1, 2027
was Aug 15, 2026
Oracle stock
close, September 24
down 3.47%
Bloomberg report day
Oracle backlog
RPO, company-wide
$664B
~13% in next 12 months
Oracle leases
not yet commenced
$288B
mostly data centres
Fuel-cell capacity and energy costs from the Oracle, BorderPlex and Bloom release of April 27, 2026. Pipeline length from the Federal Register, September 10; in-service dates from Transwestern's filings to FERC. Share price from Nasdaq historical quotes. Oracle figures from its 8-K and 10-Q for the quarter to August 31, 2026, company-wide, not Jupiter alone.
The mechanism
A data centre with its own power plant

The campus is designed to run on up to 2.45 gigawatts of Bloom Energy fuel cells, which the state air permit rates at 2,462 megawatts, and Oracle will continue to bear all energy costs. Fuel cells make electricity from natural gas without burning it in a turbine, which is why the design stands or falls on gas supply. Oracle put the dependency in its own words in a May filing to the Federal Energy Regulatory Commission: without a reliable source of natural gas, the power plant cannot function. The same filing names an Oracle subsidiary, Green Chile Ventures, as the pipeline's sole shipper.

One pipe, two separate problems

The gas comes through a 17.77-mile line proposed by Transwestern Pipeline Company, an Energy Transfer unit. The first problem was land. New Mexico's State Land Office cancelled the applications to cross state trust land in March and denied reconsideration on July 14, over less than a mile of route. Transwestern redrew the line to avoid state trust land, and it now runs mostly across federal land. That problem is behind it.

The second is the one that changed the federal timeline. Transwestern first filed under a prior notice process, a faster route for projects under an existing blanket certificate. On April 13, FERC staff protested because the filing lacked a finding from the New Mexico State Historic Preservation Office that no historic properties would be affected. Transwestern did not file it by the deadline, so the request now proceeds as a case-specific application under section 7 of the Natural Gas Act, the slower path. The office asked on April 17 for further testing at one site, and an addendum survey report went to it on August 7.

The dates moved. Transwestern's original filing targeted service on August 15, 2026. Its August data response gave a revised estimate of February 1, 2027, without giving a reason. FERC has not tied that date to either problem, and neither do we.

The permit fight on the other side

The fuel cells need their own state air permit, and that has been a fight of its own. NMED, the New Mexico Environment Department, says it must approve or deny the permit by November 23 under state statute; the applicant says that date cannot slip, and opponents say it is not a hard stop. The hearing was set for September 14. The hearing officer recused himself on August 22, and on August 23 the New Mexico Supreme Court stayed the proceeding on a petition from New Energy Economy. KRWG reported on September 18 that the court had lifted the stay, and that NMED had yet to appoint a new hearing officer or set a new hearing date.

 
PARTNER
Quarterly revenue: Oracle and Bloom Energy
TradingView's Fundamental Graphs, charting Oracle and Bloom Energy total revenue by fiscal quarter.

Oracle's remaining performance obligations and lease commitments are reported each quarter, next to its revenue. The chart above tracks Oracle and Bloom Energy's reported revenue by quarter on TradingView, and can be saved to an account ahead of the regulators' decisions in November and December. Readers who join through our link receive $15 off a TradingView subscription.

View the chart
 
What they are saying

The four statements below are the parties describing their own position, which is why they carry more weight than any outside estimate. Read the second one twice. In July an Oracle vice president told the state regulator, under oath, that Oracle's gas, power and construction agreements are contingent on certain activities commencing by December 2026. The declaration does not say which activities, or what happens if they do not begin.

What they are saying. Oracle told FERC that without a reliable source of natural gas the power plant cannot function. An Oracle vice president declared that its gas, power and construction agreements are contingent on activities commencing by December 2026. FERC moved the pipe off the fast track over the missing historic preservation documentation. Oracle's spokesperson said force majeure notices are commonplace and the project remains on its planned schedule.
What to watch
From September 27
Instrument:the two regulatory decisions that gate the power plant's gas and its permit
Level:approve or deny: NMED on the Yucca Growth air permit; FERC on Transwestern's Green Chile pipeline
Meaning:approval on both keeps the plant on a path to gas and a permit; a denial or a slip on either puts its gas, or its permit, in doubt, with Oracle's December 2026 condition behind both
Date:November 23, NMED's statutory deadline on the air permit, contested; December 3, FERC's decision deadline on the pipe
Earlier:October 5, FERC's comment window on its environmental assessment closes; the historic preservation office's reply to the August 7 survey addendum; any new NMED hearing date
Further out:February 1, 2027, Transwestern's revised in-service estimate; Oracle's next quarterly filing, where remaining performance obligations and lease commitments are reported
Deadlines from the Federal Register (July 29 and September 10, 2026) and NMED's position statement of July 22, 2026. General research, not a recommendation.
What we make of it

Three things. First, the risk in this story is sequencing, not demand. Nobody in the record doubts that Oracle wants the capacity: it reports $664 billion of remaining performance obligations and has signed a master services agreement with Bloom for up to 2.8 gigawatts of fuel cells. What the record shows is a chain in which each link has its own clock. The permit has to land before the plant can run, the pipe has to land before the plant has fuel, and the pipe has one more step after approval: FERC staff recommend that construction wait until the historic-sites consultation is complete. The two decisions due by November 23 and December 3 fall in or just before the month Oracle's own contracts name. That the dates collide is our reading, not anything a regulator or Oracle has said.

Second, the dockets will tell this story before the company does. Oracle will not report Jupiter as a line item; its $288 billion of lease commitments not yet begun are worldwide. The places a slip would show first are public and dated: FERC's order on Transwestern, NMED's ruling, a new hearing date, and the historic preservation office's reply on the August survey. A force majeure notice is a contractual step. A missed regulatory date is a fact anyone can check.

Third, time costs more than it used to. Oracle's free cash flow was negative $5 billion last quarter and it sold $20 billion of new stock, which makes it a company paying up front for capacity it will be paid for later. Our macro screen has the ten-year real Treasury yield near its highest level since the series began in 2003, so the months between building capacity and billing for it are expensive to carry. A delay of a few months at one campus does not change Oracle's picture. The same pattern repeated across a build of this size is what the lease and backlog numbers will eventually show.

The Brief goes out every Sunday morning.
How was this issue?
SharpFineMissed
 
RollOutInvestor
RollOutInvestor, Calgary, Alberta, Canada
General research, published to every reader on the same schedule. Not personal advice and not a recommendation to buy or sell any security. We may earn a commission from links to our partners.